Hi Teams,

We use PF3000 to supply i.mx7 dual processor.

The power up sequence of i.mx7 is correct.

When power off the the power supply to PF3000, the power down sequence of i.mx7 can not meet the spec. VSNVS would be turned down fast than some other power rail.

Would this violation to be acceptable?

Thanks.

0 件の賞賛
返信
2 返答(返信)

969件の閲覧回数
Manuel_Salas
NXP TechSupport
NXP TechSupport

Hello @tonywk 

 

I believe there is not problem, because that behavior is the expected. Please check the datasheet:

VDD_SNVS _IN to be turned off last after any other power supply.

Alejandro_Salas_0-1717188104256.png

 

Alejandro_Salas_1-1717188118928.png

 

Best regards, 

Salas.

 

0 件の賞賛
返信

933件の閲覧回数
tonywk
Contributor I

Hi Alejandro,

For the power down sequence of i.mx7,

VSNVS would turn off first and then the other power rails would be turn off.

Is that a problem for i.mx7?