Hi, 

I understood that there has been leadtime issue due to Covid19, we have placed subject MPU by end-JAN this year, being told that leadtime is 52-64 weeks, and will be delivery in APR-2022, which is fine.

 

However, we were just told by last week that our allocation has been pushed out to JUL-2022, which is another 3mths/ 12wks after being wait for 10 months. I do understand that is Covid19 issue, but when I check NXP page for leadtime is still 52 weeks, may I know how to find out if my allocation has been managed properly and fairly? Thanks for your time and comment.

0 Kudos
1 Reply

331 Views
igorpadykov
NXP Employee
NXP Employee

Hi Carol 

 

supply times may differ locally, please contact local marleting office for details for your case.

 

Best regards
igor