AnsweredAssumed Answered

MQX 4.2 SCHEDULING CONFIGURATION

Question asked by ANAND S on Jul 30, 2019
Latest reply on Aug 1, 2019 by Daniel Chen

Hi All,

I have doubts in mqx 4.2 scheduling. in our project we are using mqx4.0(for k60) due to code memory size issue we are moving project to K66. so switched mqx 4.0 to 4.2 as there is no support for K66 in mqx 4.0. Now we are facing issue in scheduling scheme. In mqx4.0 we are not using time slicing MQX_HAS_TIME_SLICE to 0 if we do the same in mqx4.2 program controller resetting. in mqx4.0 we are using priority based event driven scheduling scheme .

is it possible to configure the same in mqx 4.2?

if it is possible please let me know how to configure?

Thanks in advance.

 

Regards

Anand.S

Outcomes