Dear Yuri,
Hello. Thank you for your reply.
> The Datasheet provides most general approach / requirements for power
> up sequence ; the Development Guide shows recommended example of power
> sequencing.
OK. I got it.
For example, VDD_HIGH_IN and NVCC33_IO were same timing from Development Guide.
But, these can separate the power sequence from data sheet.
> Different power up sequence for LDO enable and bypass is recommended
> mainly to avoid excessive current during power-up phase.
Sorry, I didn't understand it well.
How should one disable (bypass) the LDOs at the power-up phase.
My understanding was below.
Power-up phase is during POR_B asserted and the user can't select the bypass LDOs.
Best Regards,
Keita